Track geometry measurements - TQM precision

Track geometry measurements - TQM modules calibration

Track geometry measurements - Tqm errors

Track geometry systems - comparison of results 

 

 

 

 

Track geometry measurement - TQM accuracy

In order to have a broader picture of possible and attainable accuracy of TQM track geometry readings a typical track geometry measurement accuracy expectancy goal needs to be set.
Track geometry measurement accuracy goal:
As TQM aims to replace laborious hand versine measurements, the accuracy of Generated Versine (derived from recorder measurements) must match a hand versine measurement accuracy of +/-2mm. Table A indicate (projection scale derived) expected track geometry singular measurement accuracy related to different chord lengths SB (short bases).
 

+/-2mm

+/-2mm

HV Accuracy Goal
for 10 and 20m chord

+/-2mm

+/-2mm

10m

20m

10m

20m

10m

20m

10m

20m

1m

1m

2m

2m

Length of Measuring Base

3m

3m

4m

4m

100

400

25

100

Projection Scale

11

44

6

25

+/-
0.02
mm

+/-
0.005
mm

+/-
0.08
mm

+/-
0.02
mm

Required Accuracy
of a TQM Singular Measurement

+/-
0.18
mm

+/-
0.05
mm

+/-
0.32
mm

+/-
0.08
mm

System Precision

System Calibration

System Corrections

Design

Engineering

Ref. Blocks

Temp.Control

Design

Correction

Table A. Track geometry - expected accuracy of TQM typical measurement

 

 

 

 

[mm]

Curve Radius [in metres]

 

Compiled measurement accuracy on curve of 1000m radius

HV

1m SB

2m SB

3m SB

4m SB

 

Short base

Horiz. Versine magnitude

Single measur. accuracy

Gen. Versine
on 20m chordG

2.0

62

250

562

1000

 

1.0

125

500

1125

2000

 

1m

0.12 mm

+/- 0.005 mm

50 +/- 2mm

0.5

250

1000

2250

4000

 

2m

0.50 mm

+/- 0.02 mm

50 +/- 2mm

0.2

625

2500

5625

10000

 

3m

1.12 mm

+/- 0.05 mm

50 +/- 2mm

0.1

1250

5000

11250

20000

 

4m

2.00 mm

+/- 0.08 mm

50 +/- 2mm

Table B. Versines and Radius

 

Table C. SB measurements on 1000m radius